Building Up-Branching Out
We are currently working to expand our school facility to include an early childhood learning center enabling us to serve children from 6 weeks through eighth grade to better serve the families in our community. The objective of the expansion is to further our mission of sharing Jesus’ love with many more people.
Building Update from Christ Alone
Project Proposal Specifics
The project team has developed a design from the many discussions, surveys and brainstorming sessions that have taken place with the members of Christ Alone church and school. From these sessions the team has provided renderings of the new school and church buildings.
The renderings outline a proposal of a 17,120 sq. ft. school addition, the plan allows for a new early childhood learning center with capacity for up to 65 students ages 6 months to age 4, who will be situated within 5 classrooms, plus offices for the staff, and a before and after school program that will continue for school age children. This proposed addition will provide 4 completed grade school classrooms plus a flex classroom which will allow for a classroom for each grade. Also included is a storm water run-off system with 198 parking stalls and reconfigured traffic flow to allow easy drop off and pick up of the students.

Timeline
- March 15, 2026 Completion of construction documents by Ramlow/Stein
- March 15, 2026 Submission of construction documents to DSPS[1] for approval[2]
- April 30, 2026 Solicitation of bids for construction contract[3]
- May 21, 2026 Award construction contract to qualified bidder
- Late May/early June 2026 Construction begins
- Early June 2026 Demolition of BTK buildings
- Mid July 2027 Substantial completion of project
[1] DSPS – Department of Safety and Professional Services
[2] Estimated to take 6 weeks or less
[3] Estimated to take 3 weeks
More Information
Concept Design
Quick view of some of the concept design images are here: