Building Up – Branching Out

Timeline

  • March 15, 2026                       Completion of construction documents by Ramlow/Stein
  • March 15, 2026                       Submission of construction documents to DSPS[1] for approval[2]
  • April 30, 2026                         Solicitation of bids for construction contract[3]
  • May 21, 2026                          Award construction contract to qualified bidder
  • Late May/early June 2026      Construction begins
  • Early June 2026                      Demolition of BTK buildings
  • Mid July 2027                         Substantial completion of project

[1] DSPS – Department of Safety and Professional Services
[2] Estimated to take 6 weeks or less
[3] Estimated to take 3 weeks

Progress Report

Building Up - Branching Out

Support the expansion of our ministry by building a childcare facility to be able to serve up to 65 students, infant to 4-year olds.

Give Today

Promised to Date $4,409,354.94

100%

Received to Date $4,181,877.43

95%

Gifts Outstanding $227,477.51

5%

Christ Alone - North Campus

Concept Design

Provided by Concord Development Company & Ramlow/Stein Architecture + Interiors